> news

2011-4-3   source:   browse:2147

work for frontline of sudan project proceeded in order as planning, such as the limestone breaker was on probation with material at october 10, 2009; the trial for clay breaker was at october 16, 2009, the raw material stock dump is planned to be piled at october 20, 2009, and the linkage trail for the equipments of raw material grinding and coal powder system had been finished largely. furthermore, the grinding mill were planned to be tested for running at early november as well as the stand-alone and linkage trail for cement grinding system. besides that, the probation of packaging system was in late november, and at the medium december for ignition.